Over 5km of electrical busbar energised at Magna Park!
VolkerFitzpatrick recently installed and energised over 5km of 630 to 1,250-amp busbar at Plot 520 Magna Park, a fulfilment centre in Milton Keynes.
![Magna Plot 520 Fitout7_web.jpg](/sites/vw_uk_fitzpatrick/files/styles/content_keyvisual_parallax_xsmall/public/webcomposer/8260--Magna%20Plot%20520%20Fitout7_web.jpg?h=4c1fc98e&itok=FfqAniwA)
![Magna Plot 520 Fitout7_web.jpg](/sites/vw_uk_fitzpatrick/files/styles/text_image_visual/public/webcomposer/8260--Magna%20Plot%20520%20Fitout7_web.jpg?itok=j0214nRB)
Following the construction of the 790,000ft2 facility in September 2018, the specialist fit out contract is currently one of the UK’s largest busbar projects and will feed the centre’s state-of-the-art automated mechanical handling equipment.
Plot 520 will be an omnichannel distribution centre, capable of receiving, processing and dispatching goods ordered from retail units in London, the South and South-West.
As part of the specialist fit out, our team is also in the process of installing:
- 60km of sprinkler pipework
- 33km of lighting trunking
- 19km of electrical containment
- 14,000 LED light fittings
Matt Goodier, project manager for VolkerFitzpatrick, said: “I am delighted that we have been able to take on the challenge of completing such a large and complex busbar project, as part of our work at Plot 520. The team has collaborated closely with stakeholders throughout, to ensure a high-quality delivery.”